the-source

Wellspring Academy

Secondary School Update 2010-02

Sanitation Block

Foundations were completed, waste lines installed, floor slab poured and first course of bricks were laid this month.

Library Building

Despite the rain, mud and wheelbarrows sloshing through it all, the foundations for the library were completed this month. All told, 60 bags of cement, 15 loads of large rough rock, 4 loads of course red sand, 4 loads of fine sand, and approximately 1,680 man hours of labour resulted in the foundation for the library’s main hall and 3 study rooms being completed.

We have bricks!

This month saw the delivery of 30,000 locally fired red bricks that will go towards the library and the Sanitation Block.

Landscaping

This month’s landscaping activity saw us complete two sections of the retaining wall to stop erosion and improve the aesthetics of the site.

Click here to read a full-length update

 


blog comments powered by Disqus
 
Wellspring: Empowering a New Generation

Canadian Flag Canadian Office:

The Wellspring Foundation for Education

PO Box 32112
Langley BC  V1M 2M3

Email the Canadian Office

Telephone: 604 592-5062
(time zone: GMT -8:00)

Rwandan Flag Rwandan Office:

The Wellspring Foundation for Education

PO Box 7489
Kigali, RWANDA

Email the Rwandan Office

Telephone: 011-250-788475155
(time zone: GMT +2:00)