| Secondary School Update 2010-01 |
|
The two main buildings that had steady gains through the month of January were the Outdoor Auditorium and the Sanitation Block. A temporary change and shower facility was also built for the construction crew. Outdoor AuditoriumThe foundation and retaining walls were completed along with rebar-reinforced columns, as well as the side entry walkway that will serve as the main entrance into the auditorium.Sanitation BlockThe Sanitation Block building began this month. The site layout was drawn, the trenches for the foundational walls were dug and ¾ of the foundational rock was set in place. Covered Change and ShowerThe last achievement for the month of January was a covered shower and changing quarters for the 8 full time member construction staff and 10-15 casual labourers. Click here to read a full-length update
|
|
|