the-source

Project Updates
Project Update 2010-06

This month we open our update with news of a generous donation from Big Steel Box. They’ve provided us with a 40-foot container that will be destined for Kigali in late August. Company owner, Barry Siebenga put it nicely, “we view giving a container to causes like yours just as important as buying a forklift for our own company.” Big Steel Box is an active participant in using their business to make a difference. Over the next few weeks, we will be organizing a list of supplies that will be destined for Kigali.

Library

In Rwanda, things continued to progress well on the secondary school project. As planned, the library’s gable ends were built, trusses and purlins put on. The supporting columns plus the beam to support the library’s veranda slab was poured. Unfortunately, the roofing company was plumb out of metal roof sheets that we hope will be available in early July.

Benjamin and Freddie working on one gable end of the library.Benjamin and Freddie working on one gable end of the library

Hasan welds the trusses onto metal plates in the ring beam
Hasan welds the trusses onto metal plates in the ring beam

Damasene adds the final two courses of brick above the ring beam
Damasene adds the final two courses of brick above the ring beam

The last look at the library before it has a beautiful “sky blue” roof on it!
The last look at the library before it has a beautiful “sky blue” roof on it!

Outdoor Auditorium

With more funds available through some support for the Outdoor Auditorium, we were able to get underway on pouring the massive floor, once again mixing it by hand! Over the course of three days our boys toiled under the belting sun.

The boys get “stuck in” mixing over 350 square meters of concrete floor space.
The boys get “stuck in” mixing over 350 square meters of concrete floor space.

Mixing in the foreground with the 4m x 4m sections of rebar for reinforced beams to ensure a super strong structure.

Long days of hot sun of mixing & pouring cement
Long days of hot sun of mixing & pouring cement

The boys mix it up and pour cement into the sections
The boys mix it up and pour cement into the sections

You can see the library in the background behind the major mixing station. This was the final day of the pour!

Nzabamwita works on finishing cement where  two parts of the  slab join.
Nzabamwita works on finishing cement where two parts of the slab join.

Taken in the same spot as picture on left  but two weeks has elapsed, walls are ½ complete and columns being built  up to the truss level.
Taken in the same spot as the picture above but two weeks have passed.
The walls are ½ complete and columns being built up to the truss level.

Picture on the left hand side is taken within the Outdoor Auditorium. Two classrooms & finished sanitation block are visibile in the background
Standing within the Outdoor Auditorium. Two classrooms & finished sanitation block are visibile in the background

Upcoming next month:

Library:

  • Putting the metal roof and gutters on

  • Form and pour the concrete veranda and pathway connections.

  • Welding in place the structure to hang ceilings

  • Plastering the interior of the Library

Auditorium:

  • Finish the brickwork on the columns and one end wall

  • Put handrails onto entry ramp.

Landscaping:

  • Pathways connecting classrooms, sanitation block, library and auditorium.

June Costs (in US)

$27,502 ~ Total

$521 ~ Landscaping

$226 ~ Sanitation Block

$10,615 ~ Library Building

$3,407 ~ Labour

$12,476 ~ Outdoor Auditorium

$257 ~ Other

 
Project Update 2010-05

Over the past few months most of the information highlighted has been the ‘bricks and mortar’ activity. However this month we start off with news of a $50,000 grant. These funds will go towards outfitting activities to purchase computers, biology and chemistry equipment plus various supplies to finish the secondary school.

Meanwhile, back in Rwanda we are seeing the beginnings of transition from rainy season to dry season. The brilliant green that envelops most of Rwanda for the greater part of the year begins to give way to a bit more dust. Through the month of June we will head into the dry season that will last until the end of August.

Sanitation Block Update & Re-cap

With the exception of connecting waste lines to the eventual site of a sewage treatment plant, the Sanitation Block is 99% complete.

slab

Recall Musonera and Bosco who worked throughout the night to ensure
the newly poured slab was saved due to the heavy rains in February.

trusses

Brickwork was the priority throughout the month of March, the ring beam
was poured and the trusses and purlins were put onto the building.

Completed Sanitation Block

Exterior of the completed Sanitation Block.

Completed Sanitation Block

Interior of the completed Sanitation Block

Our thanks to the Rwandan construction crew and Vernon team who raised support through various creative fundraising activities; like the high school flushathon! Your creativity, dedication and heart to help are changing lives.

Library Building:

As hoped, in May we managed to finish the library walls up to the level of the ring beam.

library-bricks

Before: Here we see the start of the library brickwork make its way up.

library-walls

After: Library at the end of May all brickwork is complete with the ring
being also completed. Next up is trusses, purlins and roof sheets.

The Vice Mayor in charge of Social Affairs from the District of Gasabo came to pay us a visit. He checked up on the progress of the Library and wondered why we weren’t doing more of this awesome work all over his district!

jeff+vice-mayor

From right to left: Jeffery, Country Director, Narcisse, Vice Mayor and Safari friend
to Vice Mayor on Wellspring Academy site looking at the Library building.

Landscaping

We continued progress to make the landscaping of our project a lot prettier and more functional.

Whereas a couple of months ago above the secondary school we just had a weed- surrounded workshop area, we have now made a landscaped area that will be planted with grass come the next rainy season.

weeds-brush-containers

Before: weeds, brush and containers were located above the secondary school building

large-trees+grass

After: large trees remain and by next rainy season grass will be planted

As part of the landscaping project, we have connected pathways from the secondary section to the primary section.

pathway

Pathway at the top of the Secondary School connects to the Primary School below

Plus connected pathways between the Secondary School Sanitation Facility and the Library. These were all completed over the past few months.

sanitation-block

Sanitation Block is 99% complete with connected pathways leading up to the Secondary
School general classroom buildings and leading down towards the Library

ss-campus

Wellspring Academy Secondary School Campus: two classroom blocks shown in left side of
above picture, Sanitation Block (not visible) behind mango trees in the center of the picture,
Library building in right background and in front of the Library is the Outdoor Auditorium.

Upcoming Next Month:

Library Building - Setting the trusses, putting on the purlins and the roof, finishing the gable ends.

Outdoor Auditorium - Pouring the entry ramp and floor and starting the brickwork

May Costs (in US)

  • $23,034 ~ Total
  • $6,020 ~ Landscaping
  • $7,515 ~ Sanitation Block
  • $7,092 ~ Library Building
  • $2,347 ~ Labour
  • $60 ~ Other

Click here to download a pdf of the full update

 
Project Update 2010-04

We once again welcome new readers from Buy a Brick, Build a School campaign that have come into contact with this project.

We start this month’s update on more of a solemn note as the month of April marked the 16th year since the ’94 genocide in Rwanda. Each April, Rwandans commemorate the genocide through a week of mourning where business, schools and government are either closed or focused on memorial services throughout Rwanda. For our construction crew working on the Secondary School, there was mixed emotion as the crew remembered what they and their countrymen endured, yet at the same time their efforts are literally focused on building the future of Rwanda. As the construction crew made there way back to work their collective determination and energy is apparent in their work that we highlight.

Christian Life Assembly, our local partner within Rwanda kindly donated the time of some staff to our project: two skilled masons, a talented welder plus his assistant and two other helpful hands that worked along side our crew for three weeks. The extra helping hands greatly aided our efforts in making solid progress within the month of April.

Sanitation Block

With the shell of the sanitation block now complete, efforts were focused on outfitting. Hassan, CLA’s welder, completed the toilet dividing walls, while others worked on connecting concrete pathways to the general purpose classrooms.

pic1 pic4 pic5

Hassan welding toilet dividing walls

David and crew connecting waste lines.

Kayumu digging down 12 meters making the septic soak tank pit

David, who this month became a proud dad of a baby boy and Bosco connected the waste lines. The last item required a deep effort on Kayumu’s behalf who dug down into the earth 12 meters with nothing more than a sawed off pick and a buddy up above with a rope and bucket to haul up the soil; the end result was the septic soak pits for our sanitation block.

pic3
Concrete pathway leading up to the nearly completed Sanitation Block

pic6
Newly installed toilet with walls freshly painted

Library Building

With all the mixing and pouring of 866 square feet of concrete completed, the crew shifted its efforts to the brickwork of the library.  The library is made up of three group workrooms and a main library hall. By the end of the month, one third of the brickwork was competed with windows and doors framed into the bricks.

pic7
The crew starts the process of laying bricks down.

pic8
Library walls make their way up, while in the background the tops of the primary schools are visible

Other Efforts

Continued progress on pathways and drainage ditch covers took place throughout the month of April. We are nearing completion in covering the drainage ditches that carry large sums of water in the rainy season plus having a well-laid pathway between the primary school (at the bottom of the campus) and the secondary school.

pic9
Pathway works its way up from the primary school to the secondary school. Parking lot is
on the left of the picture with the secondary school on the right side of the picture.

pic10
Pathway works its way down the hill to the top of the primary school shown on the right hand side of the picture. This pathway will extend down to the valley where the secondary school sports facility is scheduled to be built.

Upcoming for next month

Sanitation Block – Finalize the last details on the interior, including installation of the last few sinks and completing the toilet doors. Waste lines will need to be installed towards the location of the future Sewage Treatement Facility; a project that still requires further funding to complete.

Library – The brickwork for the library is planned to reach the ring beam level with all the doors and windows being set. Work will also start on welding the trusses for the library in their place.

Pathways – Continued work will take place in pouring cement between various buildings and landscaping the green spaces in between the various secondary school buildings.

April Costs (in US)

$23,034 ~ Total

$6,020 ~ Landscaping

$7,515 ~ Sanitation Block

$7,092 ~ Library Building

$2,347 ~ Labour

$60 ~ Other

 

Click here to download a pdf of the full update

 
Project Update 2010-03

A welcome to our new readers that joined us through their support of Buy a Brick, Build a School campaign this month!

March saw strong, steady progress towards building the Sanitation Block and Library plus continued progress on landscaping/land preparation.

Sanitation Block

The walls were pushed up with the ring beam being formed and poured this past month. The trusses and purlins were also affixed to the building in order and the roof was installed. We are nearing the end of the Sanitation Block being complete.

RW-1 RW-2
The building crew secures the trusses to the newly built up walls of the Sanitation Block. In March, the roof was laid atop the trusses and secured.

Library Building

With last month being as wet as it was, the crew was happy to have a few days of dry weather to form and pour the floor slab. Over 20 additional casual laborers joined the 18 exisiting crew for 2 tough days of mixing and pouring all 866 square feet of concrete. Next up will be doing the brickwork to push up the walls.

RW-3 RW-4
There were two brutish days of shovel mixing and pouring for the hard working crew. Library floor slab nearing completion, thankfully no sudden rains like last month when the Sanitation floor slab was poured.

A little help from our friend

Joe Cocker may not have been thinking of DJ Devries when he penned the words to his famous song, ‘A little help from our friends’ but they are nonetheless fitting. DJ, once again came out to Rwanda from Vancouver to help with the interior of the building. This time his stay was for 3 weeks. During that time the Library’s overall interior layout was designed. Ideas quickly became action with book shelves, individual study carols, book displays and the librarian’s circulation desk being built. DJ worked with Benjamin and Freddie, two of our local crew, to cut and machine all the pieces for the furniture then began assembeling many of the newly built interior shelves and desks. Through their combined efforts, we are well ahead of the curve for outfitting the library.

RW-5 RW-6
Freddie drills one of 15,000 holes over three days for the library’s adjustable bookshelves Benjamin chisels out a groove for the side of a study carol.
RW-7 RW-8
DJ inspects the side of the newly built library shelves Back to school for DJ!

Landscaping/land preparation project

March saw continued work on the campus:

  1. Prepare space for the Sanitation Block water supply tanks (below left).
  2. Started building a new shelter for the electricty distribution (below right).
  3. Continued forming and pouring for the drainage ditch covers around campus.
RW-9 RW-10
On the right side of the picture inside the formed area will rest the 30,000 liters of water that will supply the secondary school Sanitation block. Shelter being built for electric distribution.

March Costs (in US)

$19,309 ~ Total

$936 ~ Landscaping

$5,744 ~ Sanitation Block

$5,871 ~ Library Building

$1,137 ~ Library Outfitting

$87 ~ Outdoor Auditorium

$5,534 ~ Labour

Upcoming for next month

  • Sanitation Block: complete plastering walls, welding interior frames and doors for washroom stalls, putting in the supply lines, toilets and sinks.
  • Library: start on brickwork, placement of the doorframes, and welding of windows.
  • Landscaping: Work to be completed around the Sanitation block above and around the secondary school classrooms (putting in grass and hedges). Plus complete the covering of the drainage ditches with walkways between the secondary school section and the primary school section.

Click here to download a pdf of the full update

 
Project Update 2010-02

stuck-in-mud Construction Supervisor David Ngirimana (left) smiles at the irony of one of our truckloads of bricks for the sanitation facility bogged down in the mud during the “dry” season.

finish-floor-slab 6:15 am: Musonera completes the extraordinary 24-hour shift having tag-teamed with Bosco to finish the floor slab.

first-course-of-bricks
The crew works on laying out the first course of bricks for the sanitation block, watch out for the puddles.

faint-outline
In the foreground you can see the faint outline for the three study rooms plus the main area of the library behind them.

unloading
Let the unloading process begin!

Just a little “under the weather”

This may be the wettest February in the living memory of Rwanda, and our construction team found themselves cold, wet, and a little behind schedule. Usually, January and February are dry months and prove good for building foundations and pouring floor slabs. We expect the rains to come in at the end of March and throughout April, and we plan our building process accordingly. So when the downfall came this February we were really taken by surprise.

Sanitation Block

Foundations were completed, waste lines installed, floor slab poured and first course of bricks were laid this month. We had a tremendous efforts carried out by Musonera and Bosco who completed an amazing 24-hours shift after the skies opened up and down poured on the freshly poured floor slab. The two of them Construction Supervisor David Ngirimana (left) smiles at the irony of one of our truckloads of bricks for the sanitation facility bogged down in the mud during the “dry” season. ! worked hard throughout the night taking turns in the damp cold then seeking refuge in the meeting room building for a few winks of sleep and some hot chai. 6:15 am: Musonera completes the extraordinary 24-hour shift having tag-teamed with Bosco to finish the floor slab. ! Sanitation Block, continued Throughout the month of March the walls will be pushed up, ring beam poured and hopefully the roof of the sanitation block completed. Also we are working to complete the water storage and dig the main water lines to the facility.

Library Building

Despite the rain, mud and wheelbarrows sloshing through it all, the foundations for the library were completed this month. All told, 60 bags of cement, 15 loads of large rough rock, 4 loads of course red sand, 4 loads of fine sand, and approximately 1,680 man hours of labour resulted in the foundation for the library’s main hall and 3 study rooms being completed. Similar to our other The crew works on laying out the first course of bricks for the sanitation block, watch out for the puddles. original stable soil prior to laying down the foundational wall for the library.

We have bricks!

This month saw the delivery of 30,000 locally fired red bricks that will go towards the library and the Sanitation Block. Unlike previous times, bricks were available in the timeframe that was promised as subsequent times we’ve had to wait anywhere from 1 – 2 months.

Landscaping

This month’s landscaping activity saw us complete two sections of the retaining wall to stop erosion and improve the aesthetics of the site. The first retaining wall was built up by the staff-housing unit located on campus and the other was built by the parking lot.

housing-retaining-wall
View of the newly built staff housing retaining wall

parking-retaining-wall
Top view of parking lot where on the left, you can see the newly built retaining wall.

Click here to download a pdf of the full update

 
More Articles...
<< Start < Prev 1 2 3 4 5 Next > End >>

Page 4 of 5