Project Updates
Project Update 2010-07

Some good news to start off our monthly update is our successful application to Books For International Goodwill who will fill a container filled with 25,000 for our Library. We applied to this US based non-profit in late spring of this year after doing some research we learned they had already sent a container to Rwanda for the Kigali Public Library. The shipment will be going out in a few weeks from Maryland. If you are interested in donating, please send me an email. We are looking to raise $7,700 USD to cover the shipment costs. We also have another challenge in raising $12,000 USD for the 40 foot container that is due to leave in September 2010.

Library Update

As hoped, the roof is now on the Library, along with the interior walls plastered and most of the electrical supply wire has been run. The ceilings have also been installed and the veranda slab in front of the building has been poured. Excellent progress is being made.

Side profile of the Library building with freshly poured sidewalk.
Side profile of the Library building with freshly poured sidewalk.

from-classrooms
Picture taken looking down from the general purpose classrooms.
You can see Outdoor Auditorium to the right and the library to the left.

interior-of-library
Interior of the library with walls plastered along with installed ceiling

outdoor-auditorium

Outdoor Auditorium Update

Through generous donations we were able to circle back and continue our work on the Outdoor Auditorium. The brick work has now been completed.

auditorium-brickwork
Picture taken within the Outdoor Auditorium showing superb brick work.
You can also see the Library on the right and the Toilet Block on the left.

Science Block Update

The crew broke ground in July on our the Secondary Schools first science block. This building will hold both Computer Science and general Science labs. Similar to all our buildings, the crew will dig down to stable soil and then start to build up the foundation of the building.

digging-in-soil
Our crew dig into Rwandan soil in the hot summer heat. In the background
you can see the library on the right and the Outdoor Auditorium on the left.

science-lab-foundation
Science labs are off to a great start. Windows and doors are being fabricated
in the workshop while the outside crew put the foundation in place.

The Big Picture Starting to Look Good!

campus-overview
In the picture you can see the two general purpose buildings on the left,
the Outdoor Auditorium on the right and in the background is the library.

Up Next Month:

First Science Block:

  • Finishing foundations
  • Pouring the floor slab
  • Start the brickwork

Landscaping:

  • Extend the height of one retaining wall between the primary and secondary school sections.

Fill Container:

  • Receive shipment of all Biology & Chemistry equipment
  • Load all construction related hardware, material & equipment
  • Import laptops from US to go inside container

July Costs (in US)

  • $26,284 ~ Total
  • $3,515 ~ Landscaping
  • $13,807 ~ Science Building
  • $4,160 ~ Library Building
  • $2,580 ~ Labour
  • $1,383 ~ Outdoor Auditorium
  • $839 ~ Other
 
Project Update 2010-06

This month we open our update with news of a generous donation from Big Steel Box. They’ve provided us with a 40-foot container that will be destined for Kigali in late August. Company owner, Barry Siebenga put it nicely, “we view giving a container to causes like yours just as important as buying a forklift for our own company.” Big Steel Box is an active participant in using their business to make a difference. Over the next few weeks, we will be organizing a list of supplies that will be destined for Kigali.

Library

In Rwanda, things continued to progress well on the secondary school project. As planned, the library’s gable ends were built, trusses and purlins put on. The supporting columns plus the beam to support the library’s veranda slab was poured. Unfortunately, the roofing company was plumb out of metal roof sheets that we hope will be available in early July.

Benjamin and Freddie working on one gable end of the library.Benjamin and Freddie working on one gable end of the library

Hasan welds the trusses onto metal plates in the ring beam
Hasan welds the trusses onto metal plates in the ring beam

Damasene adds the final two courses of brick above the ring beam
Damasene adds the final two courses of brick above the ring beam

The last look at the library before it has a beautiful “sky blue” roof on it!
The last look at the library before it has a beautiful “sky blue” roof on it!

Outdoor Auditorium

With more funds available through some support for the Outdoor Auditorium, we were able to get underway on pouring the massive floor, once again mixing it by hand! Over the course of three days our boys toiled under the belting sun.

The boys get “stuck in” mixing over 350 square meters of concrete floor space.
The boys get “stuck in” mixing over 350 square meters of concrete floor space.

Mixing in the foreground with the 4m x 4m sections of rebar for reinforced beams to ensure a super strong structure.

Long days of hot sun of mixing & pouring cement
Long days of hot sun of mixing & pouring cement

The boys mix it up and pour cement into the sections
The boys mix it up and pour cement into the sections

You can see the library in the background behind the major mixing station. This was the final day of the pour!

Nzabamwita works on finishing cement where  two parts of the  slab join.
Nzabamwita works on finishing cement where two parts of the slab join.

Taken in the same spot as picture on left  but two weeks has elapsed, walls are ½ complete and columns being built  up to the truss level.
Taken in the same spot as the picture above but two weeks have passed.
The walls are ½ complete and columns being built up to the truss level.

Picture on the left hand side is taken within the Outdoor Auditorium. Two classrooms & finished sanitation block are visibile in the background
Standing within the Outdoor Auditorium. Two classrooms & finished sanitation block are visibile in the background

Upcoming next month:

Library:

  • Putting the metal roof and gutters on

  • Form and pour the concrete veranda and pathway connections.

  • Welding in place the structure to hang ceilings

  • Plastering the interior of the Library

Auditorium:

  • Finish the brickwork on the columns and one end wall

  • Put handrails onto entry ramp.

Landscaping:

  • Pathways connecting classrooms, sanitation block, library and auditorium.

June Costs (in US)

$27,502 ~ Total

$521 ~ Landscaping

$226 ~ Sanitation Block

$10,615 ~ Library Building

$3,407 ~ Labour

$12,476 ~ Outdoor Auditorium

$257 ~ Other

 
Project Update 2010-05

Over the past few months most of the information highlighted has been the ‘bricks and mortar’ activity. However this month we start off with news of a $50,000 grant. These funds will go towards outfitting activities to purchase computers, biology and chemistry equipment plus various supplies to finish the secondary school.

Meanwhile, back in Rwanda we are seeing the beginnings of transition from rainy season to dry season. The brilliant green that envelops most of Rwanda for the greater part of the year begins to give way to a bit more dust. Through the month of June we will head into the dry season that will last until the end of August.

Sanitation Block Update & Re-cap

With the exception of connecting waste lines to the eventual site of a sewage treatment plant, the Sanitation Block is 99% complete.

slab

Recall Musonera and Bosco who worked throughout the night to ensure
the newly poured slab was saved due to the heavy rains in February.

trusses

Brickwork was the priority throughout the month of March, the ring beam
was poured and the trusses and purlins were put onto the building.

Completed Sanitation Block

Exterior of the completed Sanitation Block.

Completed Sanitation Block

Interior of the completed Sanitation Block

Our thanks to the Rwandan construction crew and Vernon team who raised support through various creative fundraising activities; like the high school flushathon! Your creativity, dedication and heart to help are changing lives.

Library Building:

As hoped, in May we managed to finish the library walls up to the level of the ring beam.

library-bricks

Before: Here we see the start of the library brickwork make its way up.

library-walls

After: Library at the end of May all brickwork is complete with the ring
being also completed. Next up is trusses, purlins and roof sheets.

The Vice Mayor in charge of Social Affairs from the District of Gasabo came to pay us a visit. He checked up on the progress of the Library and wondered why we weren’t doing more of this awesome work all over his district!

jeff+vice-mayor

From right to left: Jeffery, Country Director, Narcisse, Vice Mayor and Safari friend
to Vice Mayor on Wellspring Academy site looking at the Library building.

Landscaping

We continued progress to make the landscaping of our project a lot prettier and more functional.

Whereas a couple of months ago above the secondary school we just had a weed- surrounded workshop area, we have now made a landscaped area that will be planted with grass come the next rainy season.

weeds-brush-containers

Before: weeds, brush and containers were located above the secondary school building

large-trees+grass

After: large trees remain and by next rainy season grass will be planted

As part of the landscaping project, we have connected pathways from the secondary section to the primary section.

pathway

Pathway at the top of the Secondary School connects to the Primary School below

Plus connected pathways between the Secondary School Sanitation Facility and the Library. These were all completed over the past few months.

sanitation-block

Sanitation Block is 99% complete with connected pathways leading up to the Secondary
School general classroom buildings and leading down towards the Library

ss-campus

Wellspring Academy Secondary School Campus: two classroom blocks shown in left side of
above picture, Sanitation Block (not visible) behind mango trees in the center of the picture,
Library building in right background and in front of the Library is the Outdoor Auditorium.

Upcoming Next Month:

Library Building - Setting the trusses, putting on the purlins and the roof, finishing the gable ends.

Outdoor Auditorium - Pouring the entry ramp and floor and starting the brickwork

May Costs (in US)

  • $23,034 ~ Total
  • $6,020 ~ Landscaping
  • $7,515 ~ Sanitation Block
  • $7,092 ~ Library Building
  • $2,347 ~ Labour
  • $60 ~ Other

Click here to download a pdf of the full update

 
Project Update 2010-04

We once again welcome new readers from Buy a Brick, Build a School campaign that have come into contact with this project.

We start this month’s update on more of a solemn note as the month of April marked the 16th year since the ’94 genocide in Rwanda. Each April, Rwandans commemorate the genocide through a week of mourning where business, schools and government are either closed or focused on memorial services throughout Rwanda. For our construction crew working on the Secondary School, there was mixed emotion as the crew remembered what they and their countrymen endured, yet at the same time their efforts are literally focused on building the future of Rwanda. As the construction crew made there way back to work their collective determination and energy is apparent in their work that we highlight.

Christian Life Assembly, our local partner within Rwanda kindly donated the time of some staff to our project: two skilled masons, a talented welder plus his assistant and two other helpful hands that worked along side our crew for three weeks. The extra helping hands greatly aided our efforts in making solid progress within the month of April.

Sanitation Block

With the shell of the sanitation block now complete, efforts were focused on outfitting. Hassan, CLA’s welder, completed the toilet dividing walls, while others worked on connecting concrete pathways to the general purpose classrooms.

pic1 pic4 pic5

Hassan welding toilet dividing walls

David and crew connecting waste lines.

Kayumu digging down 12 meters making the septic soak tank pit

David, who this month became a proud dad of a baby boy and Bosco connected the waste lines. The last item required a deep effort on Kayumu’s behalf who dug down into the earth 12 meters with nothing more than a sawed off pick and a buddy up above with a rope and bucket to haul up the soil; the end result was the septic soak pits for our sanitation block.

pic3
Concrete pathway leading up to the nearly completed Sanitation Block

pic6
Newly installed toilet with walls freshly painted

Library Building

With all the mixing and pouring of 866 square feet of concrete completed, the crew shifted its efforts to the brickwork of the library.  The library is made up of three group workrooms and a main library hall. By the end of the month, one third of the brickwork was competed with windows and doors framed into the bricks.

pic7
The crew starts the process of laying bricks down.

pic8
Library walls make their way up, while in the background the tops of the primary schools are visible

Other Efforts

Continued progress on pathways and drainage ditch covers took place throughout the month of April. We are nearing completion in covering the drainage ditches that carry large sums of water in the rainy season plus having a well-laid pathway between the primary school (at the bottom of the campus) and the secondary school.

pic9
Pathway works its way up from the primary school to the secondary school. Parking lot is
on the left of the picture with the secondary school on the right side of the picture.

pic10
Pathway works its way down the hill to the top of the primary school shown on the right hand side of the picture. This pathway will extend down to the valley where the secondary school sports facility is scheduled to be built.

Upcoming for next month

Sanitation Block – Finalize the last details on the interior, including installation of the last few sinks and completing the toilet doors. Waste lines will need to be installed towards the location of the future Sewage Treatement Facility; a project that still requires further funding to complete.

Library – The brickwork for the library is planned to reach the ring beam level with all the doors and windows being set. Work will also start on welding the trusses for the library in their place.

Pathways – Continued work will take place in pouring cement between various buildings and landscaping the green spaces in between the various secondary school buildings.

April Costs (in US)

$23,034 ~ Total

$6,020 ~ Landscaping

$7,515 ~ Sanitation Block

$7,092 ~ Library Building

$2,347 ~ Labour

$60 ~ Other

 

Click here to download a pdf of the full update

 
Project Update 2010-03

A welcome to our new readers that joined us through their support of Buy a Brick, Build a School campaign this month!

March saw strong, steady progress towards building the Sanitation Block and Library plus continued progress on landscaping/land preparation.

Sanitation Block

The walls were pushed up with the ring beam being formed and poured this past month. The trusses and purlins were also affixed to the building in order and the roof was installed. We are nearing the end of the Sanitation Block being complete.

RW-1 RW-2
The building crew secures the trusses to the newly built up walls of the Sanitation Block. In March, the roof was laid atop the trusses and secured.

Library Building

With last month being as wet as it was, the crew was happy to have a few days of dry weather to form and pour the floor slab. Over 20 additional casual laborers joined the 18 exisiting crew for 2 tough days of mixing and pouring all 866 square feet of concrete. Next up will be doing the brickwork to push up the walls.

RW-3 RW-4
There were two brutish days of shovel mixing and pouring for the hard working crew. Library floor slab nearing completion, thankfully no sudden rains like last month when the Sanitation floor slab was poured.

A little help from our friend

Joe Cocker may not have been thinking of DJ Devries when he penned the words to his famous song, ‘A little help from our friends’ but they are nonetheless fitting. DJ, once again came out to Rwanda from Vancouver to help with the interior of the building. This time his stay was for 3 weeks. During that time the Library’s overall interior layout was designed. Ideas quickly became action with book shelves, individual study carols, book displays and the librarian’s circulation desk being built. DJ worked with Benjamin and Freddie, two of our local crew, to cut and machine all the pieces for the furniture then began assembeling many of the newly built interior shelves and desks. Through their combined efforts, we are well ahead of the curve for outfitting the library.

RW-5 RW-6
Freddie drills one of 15,000 holes over three days for the library’s adjustable bookshelves Benjamin chisels out a groove for the side of a study carol.
RW-7 RW-8
DJ inspects the side of the newly built library shelves Back to school for DJ!

Landscaping/land preparation project

March saw continued work on the campus:

  1. Prepare space for the Sanitation Block water supply tanks (below left).
  2. Started building a new shelter for the electricty distribution (below right).
  3. Continued forming and pouring for the drainage ditch covers around campus.
RW-9 RW-10
On the right side of the picture inside the formed area will rest the 30,000 liters of water that will supply the secondary school Sanitation block. Shelter being built for electric distribution.

March Costs (in US)

$19,309 ~ Total

$936 ~ Landscaping

$5,744 ~ Sanitation Block

$5,871 ~ Library Building

$1,137 ~ Library Outfitting

$87 ~ Outdoor Auditorium

$5,534 ~ Labour

Upcoming for next month

  • Sanitation Block: complete plastering walls, welding interior frames and doors for washroom stalls, putting in the supply lines, toilets and sinks.
  • Library: start on brickwork, placement of the doorframes, and welding of windows.
  • Landscaping: Work to be completed around the Sanitation block above and around the secondary school classrooms (putting in grass and hedges). Plus complete the covering of the drainage ditches with walkways between the secondary school section and the primary school section.

Click here to download a pdf of the full update

 
<< Start < Prev 1 2 Next > End >>

Page 1 of 2